Substructure

Product information


The types of substructure are divided into four kinds as slingshot (dually raised- type), swing up, block package and box-on-box.
1. Drill floor and the equipments on it can be installed at low position; and the mast is erected up to vertical position while the drill floor keeps low-position, then the drill floor and the mast are lifted integrally to working position.
2. There are two hydraulic cylinders equipped on top layer of the substructure; they can be used for buffering and regulating while lifting the drill floor, and as a pushing force while laying down the drill floor.
3. It is designed into modules. For land way and railway transportation, the substructure can be disassembled into small pieces and also into large pieces for oil field transportation as well.
4.There is standby interface at the bottom layer of the substructure for integral trailer or horizontally moving device; the mast, drawworks and BOP device etc can be moved integrally. It meets the requirement of quick movement and drilling cluster well.
1. Parallelogram lifting structure is used, so drill floor and the equipments on it can be installed at low position, and lifted by the drawworks force.
2. There are two hydraulic cylinders equipped on top layer of the substructure; they can be used for buffering and regulating while lifting the drill floor, and as a pushing force while laying down the drill floor.
3. Less power is needed and stable for lifting.
1. The structural type is “tall front and low back” . The front of the substructure is taller, meeting the requirement of standard BOP installation. The back of the substructure is lower, meeting the installation requirement of heavier power equipment and drive device.
2. The main parts are big components with good rigidness, so they are stable.
1. The main structure is big box-on-box structure, the location between each layers is fixed by combination of concave and convex blocks.
2. It is simple, quick and stable for its installation.

Specification:


Type Swing up type substructure Swing up type substructure Box-on-box type substructure Slingshot type substructure Block package substructure Slingshot type substructure
Model DZ158/6-S DZ180/6-S DZ170/8.6-XD DZ225/7.5-G DZ225/7.5-K DZ315/9-G
Drill floor height m 6 6 8.6 7.5 7.5 9
Clear height under RT beam m 4.3 4.3 7.223 6.26 6.32 7.62
RT beam load kN 1580 1800 1700 2250 2250 3150
Setback load kN 870 1080 1080 1125 1440 1800
Mast bottom span m 7.5 8 8 8
Type Block package substructure Block package substructure Slingshot substructure Block package substructure Integral swing up substructure Swing up substructure
Model DZ315/7.5-K DZ315/9-K DZ450/9-G DZ450/9-K DZ450/10.5-S DZ675/12-S
Height of drill floor m 7.5 9 9 9 10.5 12
Clear height under RT beam m 6.26 7.62 7.6 7.727 9.227 10
RT beam load kN 3150 3150 4500 4500 4500 6750
Setback load kN 1800 1800 2520 2520 2520 3250
Mast bottom span m 9.11 9.11 9 9.11 8.5 10